If you know these terms, you understand every function of Piping 2D. The tasks refer here when a term matters. General terms of all plug-ins (palette, system, layer, level, drawing units) are explained in Getting started › Concepts.

The 2D pipe

A pipe in Piping 2D is an ordinary line of the CAD (or a polyline if it is flexible) – no block, no solid. It lies in the drawing plane (elevation 0) and carries its pipe data: system, system elevation, size, flexible and radius. The geometry is the line itself; whatever you change on it with the CAD is the pipe right away.

Rigid and flexible pipe

1 Rigid (plan view, bathroom of the sample plan): the pipes from the lavatory to the risers in the shaft with right-angled corners (1), each segment one line
1 Rigid (plan view, bathroom of the sample plan): the pipes from the lavatory to the risers in the shaft with right-angled corners (1), each segment one line
2 Flexible (plan view): the same pipes with rounded corners (1) – a polyline with one arc per corner
2 Flexible (plan view): the same pipes with rounded corners (1) – a polyline with one arc per corner
rigid (default)flexible
Used forcopper, steel, plastic pipe in straight lengthsbendable pipes such as PEX or multilayer pipe from the coil
In the CADone line per segmentone polyline, an arc with the radius at every corner
Cornerssharprounded with the radius (default 300 mm); if it does not fit, a smaller radius is used – shown red at the cursor
Parallel pipescorners miteredarcs concentric
Bill of materials"Pipe", length of the lines"Pipe flexible", length along the arcs
Turn on–flexible check box on the Pipe page (new pipes) or Properties (existing pipes)

Even when flexible, the pipe data reach to the corner point – only the display is rounded. Tools always write the pipe straight; the rounding is created again afterwards.

System elevation

The system elevation says in which zone of the building a pipe runs – for example in the floor, below the ceiling, in the wall. In Piping 2D it is a property, not an elevation value: everything is drawn at elevation 0. They are the same system elevations as in Piping 3D (gear menu › System elevations), with an abbreviation and a name.

Crossing and elevation change

1 Crossing (plan view, corridor of the sample plan): the pipes on the lower system elevation ("2. Lage") are broken at the crossing (1), heating supply and return on the upper one ("1. Lage") run through (2)
1 Crossing (plan view, corridor of the sample plan): the pipes on the lower system elevation ("2. Lage") are broken at the crossing (1), heating supply and return on the upper one ("1. Lage") run through (2)
2 Elevation change (plan view): at the corner in front of the shaft the pipes change their system elevation – a circle each shows the change (1); the upper one runs to the center of the circle, the lower one ends at its edge (2)
2 Elevation change (plan view): at the corner in front of the shaft the pipes change their system elevation – a circle each shows the change (1); the upper one runs to the center of the circle, the lower one ends at its edge (2)
CrossingElevation change
WhenTwo pipes cross without being joined.A pipe continues on another system elevation at a corner or branch.
What you seeThe pipe on the lower system elevation has a real gap (default 50 mm), the upper one runs through. Same system elevation: no gap.A circle around the corner (default 60 mm diameter). The upper pipe runs to the center, the lower one ends at the edge. At a tee the pipe that runs through stays whole.
How it is createdBy itself with every change (draw, move, copy, delete); can be turned off in the gear menu › Elevation marking.While drawing choose another system elevation with A, or connect to a pipe on another system elevation; likewise Change system elevation and Connect.
What it followsThe gap is set again with every change.The circle follows the moved pipe. If both pipes have the same system elevation afterwards, it disappears.

System

The system says what flows in the pipe – for example cold water, hot water, heating supply. It sets the color and the layer (for example LuaCAD_SAN_PWC-Kaltwasser reduziert). In the system definitions Piping 2D has its own list with its own display (the entries "single-line (2D pipe)" and "riser insulation circle") – independent of how Piping 3D shows the same system. Create and change them in the gear menu › Systems.

Size

Instead of a nominal size (DN) a 2D pipe carries a size in mm – optional. Empty means: no value. The size is used by the bill of materials (length per size), the annotation (field {Dimension}), the size of the riser circles (radius = half the size, without a size 50 mm) and the conversion to 3D. Where different sizes meet at a node, the bill of materials counts a reducer there.

Riser

Plan view: three rise/drop symbols in the shaft of the bathroom – cold water: the pipe circle inside the insulation circle, line and arrow pointing up (1), hot water with thicker insulation, the circle dash-dot like the pipe (2), recirculation with the arrow in the opposite direction, down (3); the pipes arrive as a branch line from the corridor (4)
Plan view: three rise/drop symbols in the shaft of the bathroom – cold water: the pipe circle inside the insulation circle, line and arrow pointing up (1), hot water with thicker insulation, the circle dash-dot like the pipe (2), recirculation with the arrow in the opposite direction, down (3); the pipes arrive as a branch line from the corridor (4)

A riser is the sign of a vertical pipe in plan view: the rise/drop symbol, a circle with a line and an arrow. In Piping 2D a riser is only its symbol – there is no vertical pipe. It carries system, size, direction, insulation and an optional riser height for the bill of materials.

DirectionWhat the symbol shows
upthe riser continues upward
downthe riser continues downward
throughit passes through the level
noneonly the circle – the riser ends here

An insulated riser gets a second circle: radius of the symbol plus insulation thickness; the arrow reaches this circle. An axis cross through the center of every riser circle is turned on and off per drawing on the Risers/connectors page. Risers have no system elevation – the pipes of parallel pipes that start at them take the system elevation of the palette.

Connector

Plan view: two free 2D connectors at the lavatory of the sample plan, cold water (1) and hot water (2), each marker in the color of its system; a pipe starts at each (3)
Plan view: two free 2D connectors at the lavatory of the sample plan, cold water (1) and hot water (2), each marker in the color of its system; a pipe starts at each (3)

A connector is the point where a pipe is to start or end – for example cold and hot water of a lavatory. Its marker (disk and ring) has the color of its system. Connectors are created in three ways: free from a connector template (Inserting connectors), with a 2D fixture from the Block Library (Fixtures), and at every outlet of a manifold.

Symbol in the pipe

Plan view: two symbols in the cold water pipe from the lavatory to the riser – a ball valve in front of the riser in the shaft (1) and a check valve in the in-wall carrier (2); the pipe is interrupted by the length of each symbol
Plan view: two symbols in the cold water pipe from the lavatory to the riser – a ball valve in front of the riser in the shaft (1) and a check valve in the in-wall carrier (2); the pipe is interrupted by the length of each symbol

A symbol – ball valve, valve, backflow preventer, pump … – sits in a gap of the pipe: it divides the pipe, the gap is as long as the symbol (default 150 mm from connector to connector), and its line drawing sits in it, in the color and on the layer of the system. A symbol with a branch (three-way valve) has three connectors; a symbol with one connector (outlet, gauge) hangs at an open pipe end. If you delete the symbol, the pipe becomes one again. When converting to 3D the symbol becomes a valve.

Manifolds and PEX pipes

Plan view, bathroom of the sample plan: a manifold with cabinet in the in-wall carrier (1), outlets in two systems (2), PEX pipes running flexibly to two pairs of connectors – shower (3) and lavatory (4)
Plan view, bathroom of the sample plan: a manifold with cabinet in the in-wall carrier (1), outlets in two systems (2), PEX pipes running flexibly to two pairs of connectors – shower (3) and lavatory (4)

A manifold (plumbing floor manifold) has outlets in one system or two systems mixed, a supply inlet and optionally a cabinet. Each outlet and the supply inlet act as connectors. PEX pipes are flexible pipes from an outlet to the connector of a 2D fixture; each remembers its outlet so that it is not assigned twice. It is the same manifold as in Floor Heating.

Piping 2D and Piping 3D

Piping 2DPiping 3D
Pipeline or polyline with pipe data, elevation 0routing line with elevation, then 3D solids
Elevationnone – only the system elevation as a propertyelevation or system elevation
Sizesize in mm, optionalnominal size (DN) from the catalog
Catalog, manufacturernonecatalog, product line, fittings
Listbill of materials with counted fittingsparts list and bill of materials
IFCnoneyes

From a finished 2D plan Piping 3D creates a 3D plan: Converting 2D to 3D. The system elevations become elevations, the symbols valves, the risers vertical risers.

2D objects and CAD commands

Pipes, rise/drop symbols, symbols, connectors, elevation change circles, elevation symbols and manifolds behave like CAD objects: grips, MOVE, STRETCH, ROTATE, MIRROR, COPY and the Properties palette work. When the command ends, Piping 2D updates everything attached – in the same undo step: