The workflow

Goal: plan a cold and hot water distribution in the basement corridor of the sample project and then change it the way it happens every day.

The example is the basement of the sample project, the plumbing drawing of level UG1: the distribution pipes run in the corridor along the corridor wall, a branch line leads through the corridor wall into shaft SA1-B, where the risers go up. Drawing is quick - this page focuses on editing:

  1. Draw the distribution pipes in the corridor
  2. Insert the risers in the shaft
  3. Connect riser and distribution pipe - tee instead of trimming
  4. Generate 3D
  5. Change the nominal size - and generate 3D again
  6. Change the elevation of a pipe
  7. Insert a ball valve in-line
  8. Read the issues
  9. Move, break, join
  10. Annotation, item numbers and list

1. Draw the distribution pipes in the corridor

Cold water (1) and hot water (2) run in the corridor along the corridor wall, on the right shaft SA1-B (3)
Cold water (1) and hot water (2) run in the corridor along the corridor wall, on the right shaft SA1-B (3)
  1. Page Pipe: system cold water (PWC), stainless steel press system, DN 32, system elevation or fixed height 2450 mm above the floor (in the basement Z = -550).
  2. Click Insert pipe, start at the left end of the corridor, press A and enter the distance to the corridor wall (here 490 mm), draw along the corridor, Enter.
  3. Do the same for hot water "PWH" (DN 32), 150 mm closer to the wall and 150 mm higher.

At first only the routing lines are drawn - thin lines in the color of the system. Pipes and fittings are created by Generate 3D (step 4). Details: Insert pipe.

Keys at the cursor

KeyEffect
Aelevation and wall offset while drawing
Spacesnap to angle / free
Enterend the run
Video coming soon: Piping 3D step 1: distribution pipes in the corridor

2. Insert the risers in the shaft

In the shaft there are two risers, cold water (1) and hot water (2); the arrows on the diagonal point up
In the shaft there are two risers, cold water (1) and hot water (2); the arrows on the diagonal point up
  1. Page Risers/connectors: choose the riser template in the list (here a template with a cold and a hot water riser DN 32, 150 mm apart - you create a template once in the Riser templates dialog).
  2. Click Insert risers/connectors. In the dialog confirm the direction "up" and the target (here the next level).
  3. The risers hang at the cursor. Space switches the riser you hold; click in the middle of the shaft.

If you are asked "Riser across levels": "Not now" keeps the riser in this drawing; you can divide it later (Divide across levels).

Video coming soon: Piping 3D step 2: risers in the shaft

3. Connect riser and distribution pipe

After Connect: the branch lines (1) lead through the corridor wall into the shaft; the distribution pipes continue and get a tee (2)
After Connect: the branch lines (1) lead through the corridor wall into the shaft; the distribution pipes continue and get a tee (2)
  1. Page Tools > Connect.
  2. Click the riser first in the shaft, then the distribution pipe along its run (not at its end).
  3. LuaCAD shows the solutions in color; the yellow one is selected. Tab pages through, Enter or a click accepts.
Video coming soon: Piping 3D step 3: connect with a tee

4. Generate 3D

After Generate 3D: pipes with insulation, the tees on the distribution pipe (1), the elbows at the foot of the risers (2)
After Generate 3D: pipes with insulation, the tees on the distribution pipe (1), the elbows at the foot of the risers (2)
  1. Page Tools > Generate 3D and click a pipe - or Enter for all.
  2. LuaCAD places pipes (in bar lengths with press couplings), tees, elbows and reducers from the catalog of the pipe and numbers the parts per riser.

More: Generate 3D, Pipe lengths.

Video coming soon: Piping 3D step 4: generate 3D

5. Change the nominal size

Before: cold water DN 32 up to the branch
Before: cold water DN 32 up to the branch
After: the supply is DN 40, the tee carries the reducer to DN 32 (1)
After: the supply is DN 40, the tee carries the reducer to DN 32 (1)

The supply from the house connector to the branch shall be DN 40:

  1. Footer Properties (or page Tools), click the cold water pipe left of the branch, Enter.
  2. In the Properties dialog set only DN to 40 and check it - the other values stay as they are. OK.
  3. LuaCAD removes the 3D of the riser network (message "3D removed - the routing lines are visible again"). Run Generate 3D again: the branch now has a tee 42 x 35 x 42 with a reducer to DN 32.
Video coming soon: Piping 3D step 5: change the nominal size

6. Change the elevation of a pipe

Before (view along the corridor): the cold water branch line at the height of the distribution pipe
Before (view along the corridor): the cold water branch line at the height of the distribution pipe
After: the branch line is 250 mm lower; a vertical is created at the tee (1), the riser is extended down to the new height (2)
After: the branch line is 250 mm lower; a vertical is created at the tee (1), the riser is extended down to the new height (2)

The cold water branch line has to pass below an obstacle, 250 mm lower:

  1. Page Tools > Change elevation, click the branch line, Enter.
  2. In the Elevation dialog enter the new elevation (absolute -800 mm or from the level).
  3. Generate 3D.
Video coming soon: Piping 3D step 6: change the elevation

7. Insert a ball valve in-line

Before: the cold water branch line without shut-off
Before: the cold water branch line without shut-off
After: the ball valve (1) sits in the branch line in front of the shaft, the pipes next to it are placed again
After: the ball valve (1) sits in the branch line in front of the shaft, the pipes next to it are placed again

Every riser needs a shut-off:

  1. Page Symbols: choose "Ball valve", Insert.
  2. Click the branch line - the ball valve is inserted in-line and slides along the pipe; click at the position you want.
  3. LuaCAD cuts the pipe, places the valve with the DN of the pipe and regenerates only the area next to it.

With a tag in the Valve dialog the valve appears in lists and in the isometric. More: Insert in-line.

Video coming soon: Piping 3D step 7: insert a ball valve in-line

8. Read the issues

The window with the issues of Generate 3D: one error with its text (1) and "Show" (2)
The window with the issues of Generate 3D: one error with its text (1) and "Show" (2)

What is not as it should be when generating 3D is built anyway - and listed bottom right in the issues list. Show zooms to the position.

Video coming soon: Piping 3D step 8: read the issues

9. Move, break, join

Video coming soon: Piping 3D step 9: move, split, join

10. Annotation, item numbers and list

Annotated with the template for system and DN: the supply PWC DN 40 (1), hot water PWH DN 32 (2) and the two branch lines (3)
Annotated with the template for system and DN: the supply PWC DN 40 (1), hot water PWH DN 32 (2) and the two branch lines (3)
  1. Page Output > Annotate: choose the template for system and DN, click the pipe, place the text.
  2. With Multiple you annotate all pipes at once - with the filter Length (for example 800 mm) short pieces at the fittings stay without text.
  3. Item numbers are created automatically per riser network when you generate 3D (1.1, 1.2 ...); make them visible with the item number template with DN.
  4. Bill of materials: combined by article, pipes with length - for example "stainless steel pipe 42 mm, 7.8 m". The table hangs at the cursor and is placed next to the plan.

More: Annotate, Item numbers, Bill of materials.